NIIGATA, Japan - Tokyo Electric Power Company Holdings Inc. said Thursday that the restart of an idle reactor at its nuclear power plant in Niigata Prefecture will be delayed by more than one year.
TEPCO had hoped to set up an antiterrorism facility for the No. 7 unit at its Kashiwazaki-Kariwa plant by August 2029, but work is behind schedule, Takeyuki Inagaki, the head of the plant, said at a press conference.
"We would like to aim for completion in April 2031," Inagaki said.
TEPCO had initially planned to complete the facility by March 2025, but the schedule was pushed back to August 2029 due to a shortage of workers and other factors.
Installing antiterror facilities, aimed at remotely cooling a reactor in emergencies, became mandatory following the 2011 nuclear disaster at TEPCO's Fukushima Daiichi nuclear power plant.
All nuclear power plants in Japan were halted following the nuclear crisis and power companies resumed reactors under stricter safety rules implemented after the disaster.
The government promotes the use of nuclear power generation, especially after energy security risks grew stronger in the wake of Russia's full-scale invasion of Ukraine.
TEPCO restarted the No. 6 unit at the Kashiwazaki-Kariwa plant in January, the first reactor to restart for the utility since the disaster.